Canadian Onshore Gas Business Unit: Journey to Maintenance Excellence

Situation

A leading Canadian integrated energy company’s Conventional Operations Business Unit, an operation that produces approximately 125,000 boe/d across four districts, was challenged with moving from 3rd-4th quartile unit cost performance to top quartile.

Senior leadership recognized that a common and consistent approach to managing maintenance work management (MWM) was critical to optimizing asset performance, reducing unit costs and realizing a sustainable culture change in maintenance and reliability (M&R).

Approach

Evolve worked with the senior leadership team and the maintenance teams at two of the four districts to drive the following:

PMO: Establishing a rigorous approach to setting a vision for the future state of M&R and managing the change journey.

Maintenance Work Management Process: Building out a common platform for identifying, planning, and executing work in the two districts and then extending the practices across the remaining two.

M&R BPMS™: Implementing a common cadence of daily, weekly and monthly M&R meetings focused on a common set of KPIs.

Coaching: Working with M&R leaders and their teams to “bring the MWM process to life” and drive common practices to realize improvements in M&R KPIs.

Results

The program achieved significant results in four key metrics for M&R:

Schedule Compliance: Improved compliance against the agreed-to schedule from 35% to 70% over five months.

Break-in Work: Reduced break-in work from 16% of work orders to 6%.

PM Compliance: Increased PM compliance from 70% to close to 100%.

M&R Spend: Realized a $1.8MM reduction in M&R spend over 6 months.

Keys to Success

Foundation Phase: It was critical to engage the districts, one of which was in a remote Northern part of the province, in a way that enrolled them in the Journey to Maintenance Excellence.

Common System and Process: Harmonizing disparate practices into a single and common process for maintenance work management created a situation where all four districts were now working on improving the same process.

Multi-site Focus: Launching the program at two sites in parallel allowed the teams to ensure a common process and system was implemented while using it as an opportunity for sites to share experiences and learn from each other.

Site-based Coaching: Developing a working partnership at the sites in implementing the journey avoided the change effort being seen as “just another initiative from HQ”.

By successfully launching the journey in two districts the client was able to enroll the remaining districts and scale the benefits.